Bjuv–Mörarp Track Replacement and Excavation
The Bjuv–Mörarp project was successfully completed, covering a total of approximately 1,000 meters of track. The primary goal of the project was to enhance infrastructure, allowing maintenance and repairs to be carried out efficiently, sustainably, and safely, while also improving safety along the route.
Project details
Location
Sweden
Client
Trafikverket
Type of contract
Main contract
Status
Completed
Duration
2024
Project Facts
1000 m of track
Total duration of 21 days
22 000 ton of materials
Executed Works and Timeline
The track closure lasted three weeks, and thanks to meticulous planning, the facility was handed back on time for the scheduled train operations. The work included sleeper replacement, ballast renewal, and extensive sub-ballast replacement on four specific sections.
Track closure timeline:
- Start Date: June 24, 2024
- End Date: July 15, 2024
- Total Duration: 21 days
Logistics and Mass Handling
The project presented a significant logistical challenge, particularly regarding mass handling. During the work period, approximately 22,000 tons of materials were transported in and out of the site, which required careful coordination and planning.
Collaboration with Trafikverket
Collaboration with Trafikverket was a key factor in the project’s success. Clear communication and fast decision-making ensured steady project progress and completion within the scheduled timeframe.