Äng – Track and Switch Replacement

The project is located in Äng, within Nässjö Municipality in Jönköping County, and aims to improve railway infrastructure in the area. The limited timeframe requires meticulous planning and efficient coordination to ensure that the work is completed on schedule and that train operations resume as planned.

Project details

Location

Sweden

Client

Trafikverket

Type of contract

Main contract

Status

Ongoing

72-hour execution period

1.200 meters of track replaced

3 switches installed

Limitied Work Peiod

The work, which will be carried out over an intensive 72-hour period, includes:

  • Track and ballast replacement on two tracks
  • Replacement of three switches to ensure more reliable and efficient train operations
  • Installation of new signal placements to optimize safety and traffic control

Additionally, approximately six overhead contact line foundations will be installed to strengthen and modernize the railway’s power supply.