Track Renewal at Aalborg Station

Aarsleff Rail carried out a comprehensive track renewal project at Aalborg Station for Banedanmark, with additional minor works at stations south of Aalborg—Skørping and Arden. The project included renewal of plain track, replacement of turnouts, and removal of redundant ones. We also rebuilt the guard rail structure south of the railway bridge spanning Limfjorden, located just north of the station.

The work was performed under partial track closures and a full track closure from July 27 to October 8, 2024.

Project details

Location

Denmark

Client

Banedanmark

Type of contract

Main contract 

Status

Completed

Project period

March 2024 – November 2024

Advisor

Niras A/S

Project Facts

8 km track renewal

44 turnouts replaced

Track lowered in preparation for electrification

39,000 tons of new ballast

Coordination with Nearby Projects

The track renewal at Aalborg Station was impacted by other projects using the same track closures. Aarsleff Rail coordinated with contractors working on ERTMS signaling installations and concrete bridge work near the station. This involved managing logistics routes, site access, and scheduling. We brought experience from similar complex projects where multiple contractors share limited closure windows to carry out parallel work efficiently. 