Track Renewal Between Odense and Nyborg

In 2023, Aarsleff Rail completed a complex renewal and speed upgrade on the double-track section between Odense and Nyborg—one of the most heavily trafficked routes in Denmark.

Project details

Location

Denmark

Client

Banedanmark

Type of contract

Main contract with early involvement

Partner/subcontractor

Per Aarsleff A/S

Status

Completed

Project period

January 2023 – October 2023

Advisor

Sweco A/S

Project Facts

23.5 km of track rebuilt (incl. welding and tamping)

21 bridges rebuilt

31 km of ballast cleaned

141.963 m³ of excavated earth, gravel, and ballast

Major Upgrade on One of Denmark’s Busiest Lines

Thanks to early involvement from 2020, we were able to contribute to the final design phase in close cooperation with Banedanmark. The result was a coordinated 10-stage delivery plan, requiring 119 days of track closures, many with only one track closed at a time. 

Between 200 and 400 people were on-site during the busiest phases, while we simultaneously delivered another large-scale track renewal project. The successful delivery of both projects demonstrates Aarsleff Rail’s organizational capacity and ability to handle high production volumes. 

Executing a Complex Operation

Aarsleff Rail led full project coordination, including contact with the client and authorities, construction and civil works, catenary and signalling, safety, and logistics. Our trusted partner Spitzke contributed machinery and personnel for mechanical track works. 

With neighboring tracks still in operation, safety and planning were paramount. Seamless coordination ensured that all work was delivered safely and efficiently, with zero compromise on the safety of our teams or passing rail traffic. 