Track Renewal Between Odense and Nyborg
In 2023, Aarsleff Rail completed a complex renewal and speed upgrade on the double-track section between Odense and Nyborg—one of the most heavily trafficked routes in Denmark.
Project details
Location
Denmark
Client
Banedanmark
Type of contract
Main contract with early involvement
Partner/subcontractor
Per Aarsleff A/S
Status
Completed
Project period
January 2023 – October 2023
Advisor
Sweco A/S
Project Facts
23.5 km of track rebuilt (incl. welding and tamping)
21 bridges rebuilt
31 km of ballast cleaned
141.963 m³ of excavated earth, gravel, and ballast
Major Upgrade on One of Denmark’s Busiest Lines
Thanks to early involvement from 2020, we were able to contribute to the final design phase in close cooperation with Banedanmark. The result was a coordinated 10-stage delivery plan, requiring 119 days of track closures, many with only one track closed at a time.
Between 200 and 400 people were on-site during the busiest phases, while we simultaneously delivered another large-scale track renewal project. The successful delivery of both projects demonstrates Aarsleff Rail’s organizational capacity and ability to handle high production volumes.
Executing a Complex Operation
Aarsleff Rail led full project coordination, including contact with the client and authorities, construction and civil works, catenary and signalling, safety, and logistics. Our trusted partner Spitzke contributed machinery and personnel for mechanical track works.
With neighboring tracks still in operation, safety and planning were paramount. Seamless coordination ensured that all work was delivered safely and efficiently, with zero compromise on the safety of our teams or passing rail traffic.